2024-04-29 · Arbor Hills Remediation Area · evidence · routine

Final Report

EGLE conducted a compliance sampling inspection at Arbor Hills Remediation Area (NPDES Permit MI0045713) on March 6–7, 2024. Composite and grab samples were collected from monitoring point 001A (manhole near the facility compositor inlet) and analyzed for suspended solids, nutrients, metals, volatile organic compounds, and semi-volatile organics. Nearly all analytes were non-detect or below regulated limits; PFOS (3.2–3.4 ng/L), PFOA (9.4–15 ng/L), and PFBS (4.3–4.6 ng/L) were detected at low levels, with no permit violations noted.

Key data point: PFOA detected at 15 ng/L and PFOS at 3.4 ng/L in grab samples collected 3/6/2024, both below federal drinking-water standards but present in landfill effluent.

2024-04-29 · Arbor Hills Remediation Area · evidence · routine

Final Report email

EGLE conducted a Compliance Sampling Inspection (CSI) at Arbor Hills Remediation Area on March 6–7, 2024, analyzing composite and grab samples from outfall 001A for conventional pollutants, metals, volatile organics, and PFAS. All measured parameters were either non-detectable or within acceptable ranges, with no violations noted during the inspection.

Key data point: No violations detected; PFOA measured at 15 ng/L and 9.4 ng/L (EGLE and facility samples, respectively, 3/6/2024), PFOS at 3.4 ng/L and 3.2 ng/L; all volatile organics and BNA compounds non-detectable.

2024-04-23 · Arbor Hills Remediation Area · evidence · notable

Organics analytical from AHLF

This is an analytical laboratory report for PFAS (per- and polyfluoroalkyl substances) testing of a wastewater sample collected from Outfall-001A at Arbor Hills Landfill on March 6, 2024. The analysis detected multiple PFAS compounds including PFBA (33 ng/L), PFPeA (18 ng/L), PFHxA (22 ng/L), PFOA (9.4 ng/L), and PFOS (3.2 ng/L), among others, while many analytes were not detected above reporting limits.

Key data point: Outfall-001A wastewater sample dated 03/06/2024 detected PFBA at 33 ng/L, PFHxA at 22 ng/L, PFPeA at 18 ng/L, PFOA at 9.4 ng/L, and PFOS at 3.2 ng/L—evidence of PFAS contamination in landfill discharge.

2024-04-19 · Arbor Hills Remediation Area · procedural · routine

Inspection photos

On March 6, 2024, inspector Sabrina Good conducted a compliance sampling inspection of the Arbor Hills Remediation Area under NPDES permit MI0045713. The photos document temporary hydrogen peroxide storage, sample handling procedures, monitoring points, and conditions at Johnson Drain.

Key data point: No specific factual readings or measurements are provided in this document; it consists only of photographic documentation without quantitative data.

2024-04-17 · Arbor Hills Energy · procedural · routine

Air Permit to Install

Arbor Hills Energy received an air permit to install (PTI 68-23A) on April 17, 2024, authorizing operation of four gas turbines and associated equipment that burn desulfurized landfill gas to generate electricity. The permit specifies emission limits for NOx, CO, SO2, VOC, and hydrogen chloride, along with detailed operating conditions, monitoring requirements, and testing protocols.

Key data point: No specific factual readings or measurements reported; this is a regulatory permit issuance document establishing permitted emission ceilings and operational requirements.

2024-04-16 · Arbor Hills Remediation Area · evidence · routine

Schedule - DMR

This is a Discharge Monitoring Report (DMR) for the Arbor Hills Remediation Area covering March 2024, filed by GFL Environmental on April 16, 2024. The report documents daily and monthly measurements of treatment pond discharge including flow, suspended solids, biochemical oxygen demand, ammonia nitrogen, phosphorus, cyanide, mercury, PFOS/PFOA/PFBS compounds, thermal discharge, temperature, pH, and dissolved oxygen. All reported parameters appear to be within permit limits or below detection thresholds.

Key data point: Discharge temperature (Final Effluent) maximum daily: 57.9°F (March 17, 2024); no permit violation or exceedance indicated.

2024-03-18 · Arbor Hills Remediation Area · evidence · routine

Schedule - DMR

This is a routine Discharge Monitoring Report (DMR) for the Arbor Hills Remediation Area covering February 2024. The report documents daily and weekly measurements of treatment pond discharge parameters including flow, suspended solids, biochemical oxygen demand, ammonia nitrogen, phosphorus, cyanide, mercury, PFAS compounds, temperature, pH, and dissolved oxygen. All reported measurements remain within permitted limits.

Key data point: No specific factual violations or exceedances reported. Temperature readings in Final Effluent (1) ranged from 31.9°F to 48°F in February 2024, all well below any concerning threshold.

2024-03-15 · evidence · routine

MK and SM handheld monitor location color coded results

A color-coded mapping of handheld air quality monitoring results at Arbor Hills Landfill locations (MK and SM monitor stations), likely showing spatial variation in air pollutants around the landfill perimeter as of March 2024.

Key data point: Document title and date confirm handheld monitoring was conducted, but specific numerical readings or color-code thresholds are not provided in the text excerpt.

2024-03-15 · Arbor Hills Remediation Area · evidence · routine

Lab report for total phenols EGLE

Merit Laboratories analyzed three wastewater samples from the Arbor Hills Remediation Area collected 03/06–03/07/2024. Total phenols were not detected in any sample (below 0.02 mg/L reporting limit); CBOD5 was also not detected (below 3 mg/L reporting limit).

Key data point: Total phenols: not detected (RL 0.02 mg/L) in all three samples; CBOD5: not detected (RL 3 mg/L) in samples S59505.02 and S59505.03, collected 03/06–03/07/2024.

2024-03-15 · Arbor Hills Landfill · procedural · routine

021224 open flare operation (EURNGTOX also shown in photo)

This document references an open flare operation at Arbor Hills Landfill with visible EURNGTOX (likely a reference identifier or equipment marking). The filing appears to be regulatory documentation from EGLE (Michigan Department of Environment, Great Lakes, and Energy) related to flaring operations and gas management.

Key data point: Open flare operation observed with EURNGTOX notation; no specific quantitative measurements or violation claims stated in the provided excerpt.

2024-03-15 · Arbor Hills Landfill · procedural · routine

Inplant at NO removal piping. A monitored leak location 021224.

EGLE filed notice of a monitored leak location within the nitrogen oxide (NOx) removal piping system at Arbor Hills Landfill on 2024-02-12. The document confirms ongoing monitoring of this inplant infrastructure component.

Key data point: Monitored leak location in NOx removal piping identified 2024-02-12; no quantitative readings provided in notice.

2024-03-15 · Arbor Hills Landfill · evidence · routine

021224 at STS ground level view of top of STS treatment vessels w/valves.

This document appears to be a photograph or visual record of the STS (likely Soil Treatment System) equipment at ground level showing treatment vessels and valves. It was filed with EGLE (Michigan Department of Environment, Great Lakes, and Energy) on March 15, 2024.

Key data point: No specific factual readings or claims present; this is a visual/photographic document of operational equipment.

2024-03-13 · Arbor Hills Remediation Area · procedural · routine

NPDES CSI-Toxics

EGLE conducted a routine NPDES compliance sampling inspection of the Arbor Hills Remediation Area (permit MI0045713) on March 5–6, 2024. The facility treats landfill-impacted groundwater through impoundment and aerated lagoon processes. The inspection found satisfactory compliance across most areas, with a marginal rating for Records/Reporting due to non-uniform significant figures in Discharge Monitoring Reports, and plans to collect additional PFAS grab samples.

Key data point: No specific measured violation or exceedance documented. Inspection rated satisfactory for permit compliance; only deficiency was procedural (DMR significant figures rounding).

2024-02-22 · Emerald RNG · procedural · routine

Air Permit to Install

This is a Permit to Install (PTI 67-23A) issued by Michigan's Air Quality Division on February 22, 2024, to Emerald RNG, LLC and Arbor Hills RNG, LLC for a renewable natural gas (RNG) plant at Arbor Hills Sanitary Landfill (SRN N2688). The facility will refine landfill gas to produce pipeline-quality natural gas using compression, dewatering, filtration, and adsorption treatment, with backup thermal oxidation and flare control devices.

Key data point: RNG plant designed to process up to 10,000 scfm of landfill gas; thermal oxidizer (EURNGTOX) must operate at minimum 1,450°F; NOx limit 0.06 lb/MMBTU hourly and 11.1 tpy; CO limit 0.20 lb/MMBTU hourly and 37.0 tpy.

2024-02-20 · procedural · routine

Test platform from ground level

This document is a test platform baseline from ground level dated February 20, 2024, filed with EGLE. No substantive environmental data, measurements, or regulatory findings are provided in the text.

Key data point: No specific factual readings or claims are extractable from this document.

2024-02-20 · evidence · routine

Base of RNGTOX day of testing 2-13-24

This document is an EGLE testing record from February 13, 2024, documenting field measurements at the base of the RNGTOX (Rapid NGT Oxidation eXperiment) testing location at Arbor Hills Landfill. The record captures subsurface conditions on the day of testing.

Key data point: The document title indicates testing was conducted on 2-13-24 at the RNGTOX base location, but the text body provided contains no specific quantitative readings or findings.

2024-02-20 · procedural · routine

Form in control room / operator record of process data

Operator record of process data filed with EGLE on 2024-02-20. No substantive details are provided in the submission to evaluate.

Key data point: Document is a procedural filing stub with no specific factual readings or measurements stated.

2024-02-20 · Arbor Hills Landfill · procedural · routine

Test date 2-13-24 during testing

EGLE testing was conducted on 2-13-24. The document is a test record filed on 2024-02-20.

Key data point: No specific factual readings or measurements are provided in this document fragment.

2024-02-20 · Arbor Hills Landfill · procedural · routine

Form in control room / operator record of process data

A blank or template form from EGLE for recording landfill operator process data in the control room, filed 2024-02-20. No actual measurements or data entries are present in this document.

Key data point: This document contains no specific factual readings or claims.

2024-02-20 · Arbor Hills Landfill · evidence · routine

Base of RNGTOX on test date 2-13-24

EGLE test results from the base of RNGTOX (a landfill gas extraction and treatment system component) dated 2-13-24. The document appears to be a technical sampling report filed on 2024-02-20, though the full analytical results are not included in the excerpt provided.

Key data point: Test date 2-13-24 for RNGTOX base-level sampling; specific analytical results not visible in this excerpt.

2024-02-20 · Arbor Hills Landfill · procedural · routine

Form filled out by operator in Control Room

A control room operator form filed with EGLE on 2024-02-20. The document name and type are noted but no substantive content or specific readings are provided in the excerpted text.

Key data point: No specific factual readings or claims are present in the provided excerpt.

2024-02-20 · Arbor Hills Landfill · procedural · routine

Test platform on TOX from ground level

Incomplete EGLE document titled 'Test platform on TOX from ground level' with minimal substantive content. The document appears to be a placeholder or header without full details of testing protocols, results, or findings.

Key data point: No specific factual readings or claims present; document header only.

2024-02-20 · Arbor Hills Landfill · procedural · routine

Test day, Open Flare next to TOX unit. Operated majority of testing.

EGLE test day was conducted on 2024-02-20 for an open flare facility located next to a TOX (toxic air) monitoring unit. The operator ran the majority of testing during this event.

Key data point: No specific factual readings or measurements provided.

2024-02-19 · Arbor Hills Remediation Area · evidence · routine

Schedule - DMR

This is a Discharge Monitoring Report (DMR) for the Arbor Hills Remediation Area treatment pond for January 2024, submitted under NPDES permit MI0045713 v6.0. The report documents daily and monthly monitoring of effluent quality parameters including flow, suspended solids, biochemical oxygen demand, ammonia nitrogen, phosphorus, cyanide, mercury, PFAS compounds, temperature, pH, and dissolved oxygen. All reported measurements appear to be within or below permit limits.

Key data point: Temperature readings in final effluent ranged from 35.4°F to 40.6°F during January 2024; mercury detected at 1.7 ng/L on 1/10/2024 (quarterly measurement); no exceedances of major permit limits documented.

2024-02-13 · Arbor Hills Landfill · evidence · routine

Site

This is an air emission compliance test report for Emerald RNG's waste gas thermal oxidizer (TOX) at Arbor Hills Landfill (SRN N2688), conducted February 13, 2024. The TOX burned waste gas from the renewable natural gas plant and was tested for NOx, CO, and NMOC emissions to verify compliance with Permit to Install 67-23A and federal MSW NSPS standards. All measured pollutant emission rates were below their allowable limits.

Key data point: TOX exhaust temperature 1,748°F average (three-test average); NOx 0.82 lb/hr (limit 0.06 lb/MMBtu); CO 3.77 lb/hr average (limit 0.20 lb/MMBtu); NMOC 0.01 ppmvd as hexane @ 3% O2 (limit 20 ppmvd) — all in compliance.

2024-02-13 · Arbor Hills Landfill · evidence · notable

Test Observation

EGLE conducted on-site observation of a scheduled stack test of the Emerald RNG LLC thermal oxidizer (EURNGTOX) at Arbor Hills Landfill on February 13, 2024, as required by Permit to Install 67-23. Testing measured NOx, CO, O2, and NMOC/VOC emissions; CO spikes were observed during operation but final estimates indicated compliance with emission limits. The RNG plant experienced operational issues the prior day related to pipeline quality and required repairs before testing could proceed.

Key data point: CO emissions spiked to ~800 ppm initially during Run #1, then fell to ~64 ppm at end of Run #1; final estimate indicated compliance with 0.20 lb/MMBTU CO limit; TOX operating at 1700°F (above minimum required 1450°F); NOx measured at approximately half the 0.06 lb/MMBTU limit.

2024-02-12 · Arbor Hills Landfill · evidence · notable

On-Site Inspection

On February 12, 2024, EGLE Air Quality Division conducted an unannounced inspection of the Emerald RNG / Arbor Hills RNG facility (renewable natural gas plant). Inspectors observed significant odors and methane emissions from the Sulfur Treatment System (STS) carbon vessels, measuring up to 5000 ppm·m of methane and hundreds of ppm in the surrounding area, along with numerous minor leaks inside the building (mostly ~300 ppm, one ~10,000 ppm). The facility's response investigations did not replicate the findings, but AQD recommended further monitoring and improved recordkeeping.

Key data point: Methane laser smart device measured 5000 ppm·m from STS Vessel 301 vents; SEM5000 measured several hundred ppm in wide area; estimated 10,000 ppm leak from interior equipment; 600–1000 ppm·m exiting building roof vents—all Feb 12, 2024.

2024-01-18 · Arbor Hills Landfill · evidence · notable

Violation Notice

EGLE issued a violation notice to Arbor Hills Energy on January 18, 2024, for unpermitted operation of gas turbines and failure to comply with diesel fuel limitations and air emissions testing requirements. During October 2023 performance testing observations, inspectors documented the facility using diesel fuel during routine operation beyond the permitted 10-minute-per-hour startup window, and the facility's NOx testing failed to meet federal standards by testing only at maximum load instead of multiple loads as required.

Key data point: October 17, 2023: visible black smoke emissions from Turbines 1 & 2 for >10 minutes due to unpermitted fuel-switching during routine operation; October 18, 2023: similar event; December 18, 2023: submitted NOx test results conducted only at maximum load, violating 40 CFR 60.335(b)(2) requirement for testing at multiple loads.

2024-01-16 · Arbor Hills Remediation Area · evidence · routine

Schedule - DMR

This is a December 2023 Discharge Monitoring Report (DMR) for the Arbor Hills Remediation Area treatment pond (Permit MI0045713 v6.0), documenting daily and summary measurements of flow, suspended solids, biochemical oxygen demand, ammonia nitrogen, phosphorus, cyanide, mercury, PFOS/PFBS/PFOA, temperature, pH, dissolved oxygen, and outfall observations. The report shows sporadic sampling with many data gaps marked as *E (equipment problems) and *F (facility issues), but measured values where available appear to fall within permitted limits.

Key data point: Temperature readings from treatment pond effluent ranged from 34.7°F to 42.8°F in December 2023, all within permit requirements; PFOS, PFBS, and PFOA detected at 0.0021, 0.0078, and 0.017 µg/L respectively.

2024-01-10 · Arbor Hills Landfill · procedural · notable

Air Other Evaluation

EGLE issued a 2nd Violation Notice and Demand for Stipulated Penalties to Arbor Hills Landfill on January 10, 2024, under Consent Judgment No. 2020-0593-CE. The facility was documented as in Non-Compliance status by the Air Quality Division. This formal enforcement action represents an escalation in the regulatory response to ongoing violations at the site.

Key data point: 2nd Violation Notice and Demand for Stipulated Penalties issued January 10, 2024 under Consent Judgment No. 2020-0593-CE; facility marked Non-Compliance

2024-01-10 · Arbor Hills Landfill · evidence · notable

Air Other Evaluation

EGLE's Air Quality Division reports on enforcement and compliance activities at Arbor Hills Landfill as of January 2024, documenting perimeter air monitor exceedances near Cell 6, a Consent Judgment mandate to install gas collection by January 18, 2024, and ongoing odor complaints including 44 complaints on December 15, 2023. The agency confirms Cell 6 corrective actions are underway and notes that MMD has issued violation notices and stipulated penalty demands.

Key data point: 44 odor complaints received on December 15, 2023; perimeter monitor exceedances near Cell 6; gas collection system ordered installed by January 18, 2024 per 2022 Consent Judgment.

2024-01-10 · Arbor Hills Landfill · evidence · urgent

Violation Notice

EGLE issued a second violation notice to Arbor Hills Landfill on January 10, 2024, for failure to implement promised odor mitigation fans despite documented nuisance odors on November 1–2 and December 7, 2023. The violation breaches Consent Judgment No. 2020-0593-CE, and Arbor Hills is ordered to pay $1,500 in stipulated penalties and demonstrate full remediation within 30 days.

Key data point: Nuisance odors documented on November 1–2 and December 7, 2023, in Cell 6 during waste filling; odor mitigating fans not operating despite Arbor Hills' October 28, 2023 commitment to use them; violation of Consent Judgment CJ No. 2020-0593-CE Paragraph 5.17.D; $1,500 stipulated penalty demand.

2023-12-27 · procedural · routine

CM9 Folder: MI-ROP-N2688-2011a - AA1 - Arbor Hills Landfills Incorporated

This is a 113-page Renewable Operating Permit (ROP) and Permit to Install (PTI) issued January 24, 2011 (revised March 28, 2018) by Michigan's Air Quality Division to Advanced Disposal Services Arbor Hills Landfill, Inc. (SRN N2688) in Northville, Michigan. The permit establishes operational, design, monitoring, and reporting requirements for the landfill's active gas collection system, treatment equipment, enclosed flares, and cold cleaner operations under federal NSPS WWW and NESHAP standards.

Key data point: No specific factual readings or measured data provided; this is a regulatory permit document stating operational and design standards, not a report of actual site conditions or violations.

2023-12-27 · Arbor Hills Landfill · procedural · routine

CM9 Folder: MI-ROP-N2688-2011a - AA1 - Arbor Hills Landfills Incorporated

This is the staff report and administrative amendment for Michigan's Renewable Operating Permit (ROP) No. MI-ROP-N2688-2011a for the Veolia / Advanced Disposal Services Arbor Hills Landfill, a 337-acre municipal solid waste landfill in Salem Township, Washtenaw County. The permit consolidates air quality requirements for landfill gas collection, treatment, and combustion systems, including gas turbines and flares. An administrative amendment in March 2018 reflected ownership changes from BFI to Advanced Disposal Services.

Key data point: No specific measured temperature, CO, or odor data provided. Document is a regulatory permit framework; 2009 emissions inventory reported 186.34 tons/year CO and 132.04 tons/year NOx from the stationary source overall.

2023-12-19 · Arbor Hills Landfill · evidence · notable

Violation Notice

Arbor Hills submitted an updated response to EGLE's November 3, 2023 violation notice regarding ongoing odor nuisance complaints, specifically addressing an October 25, 2023 violation tied to inadequate odor mitigation during daily cover removal. The company claims its perimeter monitoring system showed no alarms on November 2, 2023 when strong odors were detected downwind, and reports additional remedial actions including new vacuum lines, expanded staffing, and third-party gas-system review.

Key data point: Strong garbage/landfill gas odors detected downwind from active filling area on November 2, 2023, despite odor mitigating fans; EGLE found the remedial response inadequate and ordered additional corrective actions.

2023-12-19 · Arbor Hills Landfill · evidence · notable

Air Other Evaluation

An EGLE Air Quality Division activity report documenting a December 19, 2023 non-compliance status at Arbor Hills Landfill following a November 3, 2023 violation notice for inadequate odor mitigation. The facility's response to odor complaints from daily cover removal was deemed insufficient; EGLE required additional remedial actions and scheduled a January 4, 2024 meeting to resolve the matter.

Key data point: Strong garbage/landfill gas odors detected downwind from active filling area on November 2, 2023, despite facility's claimed use of odor mitigating fans; EGLE determined odor mitigation measures inadequate and required additional remedial actions.

2023-12-13 · Arbor Hills Remediation Area · procedural · routine

Submission PDF

GFL submitted a certification stating that all additional monitoring requirements under permit MI0045713 for the Arbor Hills Remediation Area were completed in compliance with permit conditions during the week of December 4, 2023. Laboratory reports were not yet available at the time of submission, but the operator certified that all parameters were monitored using acceptable quantification levels and analytical methods.

Key data point: No specific factual readings provided; certification only that sampling was completed the week of December 4, 2023, with lab reports pending.

2023-12-11 · Arbor Hills Remediation Area · procedural · routine

Schedule - DMR

This is a Discharge Monitoring Report (DMR) for the Arbor Hills Remediation Area treatment pond covering November 2023. The report documents compliance with permit MI0045713 v6.0 across multiple water-quality parameters including suspended solids, biochemical oxygen demand, ammonia nitrogen, phosphorus, cyanide, mercury, PFOS/PFBS/PFOA, temperature, pH, and dissolved oxygen. The report shows "No Discharge: Y" for all monitoring periods, indicating no effluent was released during the month.

Key data point: No discharge occurred during November 2023; all daily and periodic monitoring parameters (suspended solids, CBOD5, ammonia, phosphorus, cyanide, mercury, PFOS/PFBS/PFOA, temperature, pH, dissolved oxygen) were tracked per permit requirements but no actual readings are provided in the document as submitted.

2023-11-13 · Arbor Hills Remediation Area · procedural · routine

Schedule - DMR

This is a routine monthly Discharge Monitoring Report (DMR) for the Arbor Hills Remediation Area's treatment pond outfall for October 2023. The facility reported "No Discharge" (Y) for the month, meaning no effluent was released. The document lists permitted limits and monitoring requirements for flow, suspended solids, biochemical oxygen demand, ammonia nitrogen, phosphorus, cyanide, mercury, PFOS/PFBS/PFOA, temperature, pH, dissolved oxygen, and visual observations.

Key data point: No discharge reported for October 2023; all monitoring parameters marked as "No Discharge: Y" with no actual measurement data provided.

2023-11-03 · evidence · notable

Violation Notice

EGLE issued Arbor Hills a Violation Notice on November 3, 2023, documenting nuisance landfill gas odors detected on Napier Road (November 1) and along 6-Mile Road (November 2). Arbor Hills responded that odors were from typical daily cover removal operations in Cell 6A and that existing odor mitigation fans were insufficient, requiring additional remedial actions within 10 days per the Consent Judgment.

Key data point: Nuisance garbage/landfill gas odors documented on 6-Mile Road between Napier Road and compost operation entrance, November 2, 2023, 6:40–7:40 a.m., downwind from active filling area.

2023-11-03 · Arbor Hills Remediation Area · evidence · routine

Violation Notice

GFL Environmental commissioned a soil remediation evaluation of Pond 2 at Arbor Hills Landfill following removal of contaminated soil containing PFAS (per- and polyfluoroalkyl substances). Six soil samples collected in November 2022 from six locations around the pond bed were analyzed for PFAS and fractional organic carbon (FOC). The analysis found only one sample (Pond 2-East) with detectable PFOS at 180 ng/kg, which remains below the EGLE Part 201 protective criterion of 1,400 ng/kg for drinking water.

Key data point: Pond 2-East soil sample contained PFOS at 180 ng/kg (below EGLE Part 201 limit of 1,400 ng/kg); five other samples showed no detectable PFOA or PFOS.

2023-11-03 · Arbor Hills Landfill · evidence · notable

Violation Notice

EGLE issued a violation notice on November 3, 2023, for nuisance odors documented on November 1–2, 2023, at Arbor Hills Landfill. Staff received approximately 30 odor complaints and conducted inspections that confirmed landfill gas odors along Napier Road and 6-Mile Road. The Landfill's proposed mitigation (odor-control fans during daily cover removal) was found inadequate, triggering a requirement for additional remedial actions within 10 days.

Key data point: Approximately 30 odor complaints received evening of November 1, 2023; nuisance landfill gas odors confirmed on Napier Road and 6-Mile Road despite odor-mitigating fans (October 25 and November 1–2, 2023 violations under Consent Judgment 2020-0593-CE).

2023-10-30 · Arbor Hills Landfill · evidence · notable

apparent switch to diesel mid-operation. visible emissions observed by TPU.

TPU (Tribal Prosecution Unit or similar environmental inspector) observed visible emissions from the Arbor Hills Landfill during apparent mid-operation switching to diesel fuel, filed as an EGLE observation on 2023-10-30. The incident suggests potential air quality violations and uncontrolled combustion byproducts. No specific temperature or emissions measurements are provided in the filing summary.

Key data point: Visible emissions observed during apparent diesel fuel switch mid-operation, filed with EGLE 2023-10-30; no quantitative measurements provided.

2023-10-27 · Arbor Hills Landfill · procedural · routine

In plant control room. All turbines shown

This document appears to be a placeholder or metadata entry referring to an in-plant control room display of turbines, filed with EGLE on 2023-10-27. No substantive environmental data, measurements, or regulatory content is present in the provided text.

Key data point: No specific factual reading or claim is stated in this document.

2023-10-27 · Arbor Hills Landfill · procedural · routine

In plant control room. All turbines shown.

This is a metadata stub or file label indicating a photograph or visual record from an in-plant control room showing all turbines, filed 2023-10-27. No substantive data, measurements, or regulatory content is present.

Key data point: No specific factual reading or claim provided; document appears to be a file reference only.

2023-10-27 · Arbor Hills Landfill · procedural · routine

RNG new control screen 2

This appears to be a placeholder or incomplete document stub labeled as an EGLE (Michigan Department of Environment, Great Lakes, and Energy) RNG control screen submission dated October 27, 2023. The document contains no substantive text, data, or regulatory content beyond its header.

Key data point: No specific factual readings or claims are present in this document.

2023-10-27 · Arbor Hills Landfill · procedural · routine

RNG new screens

Document references EGLE involvement with RNG (renewable natural gas) screening at Arbor Hills Landfill. Insufficient detail provided to determine substantive content or regulatory significance.

Key data point: No specific factual reading or data point available in provided text.

2023-10-27 · Arbor Hills Landfill · procedural · routine

Digital screen at the T4.

This document is a header or metadata entry for a digital screen display located at the T4 (tipping area 4) of Arbor Hills Landfill, filed with EGLE on 2023-10-27. No substantive content, measurements, or regulatory information is provided.

Key data point: No specific factual claim or data is present in this document.

2023-10-27 · Arbor Hills Landfill · evidence · notable

EGT1 and EGT2 abrupt switch to diesel; visible emissions Andrew Riley

On an unspecified date in October 2023, the dual Enclosed Ground Treatment (EGT) units at Arbor Hills abruptly switched to diesel fuel operation and produced visible emissions. Andrew Riley, likely an EGLE inspector, documented this observation.

Key data point: EGT1 and EGT2 switched to diesel operation with visible emissions observed; no quantitative readings or date precision provided.

2023-10-27 · Arbor Hills Landfill · procedural · routine

On turbine

This document appears to be a brief reference or header line noting 'On turbine' as an nSITE document type from EGLE, dated 2023-10-27. No substantive environmental data, measurements, or regulatory content is provided.

Key data point: No specific factual reading or claim present; document is too minimal to extract a citable data point.